The contract that will transform the ITER platform into one of Europe’s biggest engineering sites has been signed between Fusion for Energy (F4E) and COMSA EMTE, a Spanish company with a proven track record in the field of construction.
 
ITER site adaptation works 3D view
AssetViewer.aspx?AssetId=55070&CultureCode=en&MaxWidth=800&MaxHeight=400
Credit: ITER
 
The objective of the contract, which is expected to run for at least one year and with a budget of approximately 11 million EUR, is to make the necessary adaptations on the ITER site in order to develop roads for the transport of material and equipment, extend power supply and water distribution, deliver the required amenities for a workforce of 3,000 people and streamline all protocols for safety, security and access to the site.

It is envisaged that over the next eight years, 39 buildings and facilities will be built on the ITER site. Construction already started last year with the erection of the Poloidal Field Coils building and the excavation of the Tokamak complex, bringing together a workforce of 275 people. 
 
By late 2012, the personnel directly involved in construction is expected to grow by roughly four times exceeding 1,000 people and by mid-2014 it is expected to triple reaching its maximum capacity of 3,000. The ITER site will therefore have to be redeveloped to accommodate the needs of the rapidly growing workforce and guarantee an optimal use of space to the different companies operating on the ground in order to carry out the construction of all facilities in parallel and on time.

The planning and development of a road network connecting traffic lanes, bus routes, pedestrian ways and parking, is estimated to be in the range of 35,000m2 and is expected to be one of the first noticeable changes on the site. A parking area reaching the capacity of 700 spaces in total together with brand new fencing, gates and external lighting will also be one of the site’s improvements. An integrated system managing access to the site, putting an end to different protocols, will be deployed together with a new safety and security system. The wider distribution of power supply, potable water and provisions for both surface and waste water drainage will be carried out.
 
In order to meet the requirements of different contractors in terms of provisional offices, amenities, dining rooms and storage for equipment and materials COMSA EMTE will be in charge for redeveloping these areas accordingly. In parallel, a central canteen catering up to 1,500 meals per day will operate together an infirmary. Also in line with the health and safety recommendations, a helipad will be available.

Contacts and sources:
Fusion For Energy

You need to be a member of Ashtar Command - Spiritual Community to add comments!

Join Ashtar Command - Spiritual Community

Email me when people reply –

Replies

  • ineresting info.  Thanks Ravinder.  You post very interesting materials that I would not have otherwise stumbled upon.  The other day you posted something on the genetic engineering stuff going on with putting human DNA in animals...That post got me doing a lot of reading about that....and I think it is awful and just asking for troubles.....Thanks for all the great and interesting posts. 
This reply was deleted.

Topics by Tags

Monthly Archives

Latest Activity

Bluesword Angel left a comment on Comment Wall
"Adrian_de_la_serna Do you have any updates for us

Yes possibility that this is week for ascension is extremely high. Father Source has given mother terra full permission to do maximum terraforming on the surface with no more obstructions! It won't…"
3 hours ago
AlternateEarth posted a blog post
"My boss told me to have a good day... so I went home." "Why don't scientists trust atoms? Because they make up everything." "I was wondering why the baseball kept getting bigger... then it hit me." "I used to be addicted to the hokey pokey... but…
8 hours ago
AlternateEarth posted a blog post
   The oceans on our planet have never been this hot, and this is causing explosive weather throughout the world. Record high temperatures are being set all over the northern hemisphere, we are witnessing absolutely crazy storms, and gigantic…
8 hours ago
Justin89636 replied to Justin89636's discussion Anything Health Related
"More info provided by Movella. -174 Hz The foundation of energetic healing. Provides a sense of security, safety and foundational comfort.

-285 Hz Shifts the energy field. Associated with cellular healing, quantum field influence and restoring…"
9 hours ago
Andromedaner Z left a comment on Comment Wall
"Ok, thank you!"
9 hours ago
Movella left a comment on Comment Wall
"There are plenty of YouTube videos that combine multiple HZ tones, which is a highly effective method used to provide optimal restoration. Whether you prefer digital soundscapes or sound bowls, the effect is the exact same. The frequencies I’ve…"
9 hours ago
Justin89636 commented on Justin89636's blog post The Arcturians And The Arcturian Solar System
"Sheldan Nidle talks here about his Arcturian contact Supa and her fellow Arcturians. https://youtu.be/o4gwrMeDaJE?si=yg5CuTR41ZfX0cHf"
9 hours ago
Drekx Omega left a comment on Comment Wall
"I like this group synergy......Each member provides an activation Impetus, or pieces of the puzzle, for the planned solution...✅..."
10 hours ago
More…

Tragedy Tomorrow, Comedy Tonight!


"My boss told me to have a good day... so I went home."
"Why don't scientists trust atoms? Because they make up everything."
"I was wondering why the baseball kept getting bigger... then it hit me."
"I used to be addicted to the…

Read more…
Views: 13
Comments: 0